Choose the correct answer from the alternatives given.
15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days. How many days will 10 men and 10 boys take to complete the remaining work?
(a). 10
(b). 8
(c).12
(d). 9
Answer
684.9k+ views
Hint:– Break down each phrase of the question to understand it better. Then find out the rate at which the work is completed with respect to boys, men. Also, find out the amount of work that can be done in one day by men and boys. Change it into one parameter to get the answer.
Complete step-by-step solution -
Given Data – 15 men can do the work in 10 days
∴One day work is completed by 15 × 10 men = 150 men.
Also, 20 boys can complete the work in 15 days
∴In one day the work is completed by 20 × 15 = 300 boys.
∴Work of 150 men = Work of 300 boys
⟹Work of one man = = Work of 2 boys
⟹Work of 10 men = 2 × 10 = Work of 20 boys
We should find out work done by 10 men and 10 boys = 10(2) + 10 = 30 boys
Also given, 20 boys do the work in 15 days
⟹30 boys can do it in =10 days.
Hence, Option A is the correct answer.
Note:–The key to solving this type of question is to understand exactly what was given and make relations accordingly. Then we find out the rate at which the work can be done with respect to each parameter. Then build a relation for the two parameters and convert everything into a single parameter to determine the answer.
Complete step-by-step solution -
Given Data – 15 men can do the work in 10 days
∴One day work is completed by 15 × 10 men = 150 men.
Also, 20 boys can complete the work in 15 days
∴In one day the work is completed by 20 × 15 = 300 boys.
∴Work of 150 men = Work of 300 boys
⟹Work of one man = = Work of 2 boys
⟹Work of 10 men = 2 × 10 = Work of 20 boys
We should find out work done by 10 men and 10 boys = 10(2) + 10 = 30 boys
Also given, 20 boys do the work in 15 days
⟹30 boys can do it in =10 days.
Hence, Option A is the correct answer.
Note:–The key to solving this type of question is to understand exactly what was given and make relations accordingly. Then we find out the rate at which the work can be done with respect to each parameter. Then build a relation for the two parameters and convert everything into a single parameter to determine the answer.
Recently Updated Pages
A boat goes 24 km upstream and 28 km downstream in class 10 maths CBSE

Write any three differences between metals and nonmetals class 10 social science CBSE

Amit standing on a horizontal plane finds a bird flying class 10 maths CBSE

Two circles of radii 5 cm and 3 cm intersect at two class 10 maths CBSE

Solve the following i John and Jivanti together have class 10 maths CBSE

What is the relation between orthocenter circumcentre class 10 maths CBSE

Trending doubts
Explain the Treaty of Vienna of 1815 class 10 social science CBSE

10 examples of evaporation in daily life with explanations

What is the full form of POSCO class 10 social science CBSE

Make a sketch of the human nerve cell What function class 10 biology CBSE

Differentiate between Xylem and phloem class 10 biology CBSE

Identify the feminine form of noun nephew a shenephew class 10 english CBSE